1. Soft Gel Capsule Machine adopts intermittent motion and multi-station hole plug metering method. It is a fully automatic capsule filling equipment that integrates capsule turning, dividing, filling, rejecting, closing, and product launching processes.

2. Operators and maintenance and repair personnel should strictly follow the operating regulations and overhaul regulations to operate, and must not operate in violation of regulations to ensure normal production.

3. The parts on the countertop are not allowed to be cleaned with solvents such as gasoline, kerosene, acetone, etc. They can be cleaned and wiped with a muslin cloth or absorbent cotton dipped in alcohol. The higher is 1200 grains/min.

4. Each adjustment mechanism and electrical parts must be flexible and reliable. It is strictly forbidden to touch the operating parts with hands or objects during the operation of the machine, and it is forbidden to clean the touch screen with water.

5. The operator should fill each refueling point with food-grade lubricating oil once a week, and apply food-grade lubricating grease on the working surface of the inner cam roller once a week.

6. Add new oil to the transmission reduction box every six months, and change the lubricating oil every two years (Shell 68# gear oil)

7. It is strictly forbidden to rub the rotating parts with hands or objects during the operation of the equipment to prevent danger.

8. Every time the mold is changed, the handwheel of the main motor must be pulled by hand before starting the machine to make the machine run for 1 to 2 revolutions. The machine is required to operate flexibly and without abnormal resistance before it can be turned on and put into production. Note: 1). The glass door must be closed during automatic operation. If the plexiglass door is opened, the safety indicator light is off, and the machine will stop changing. 2). If the vacuum pump is not turned on first during automatic operation, the main motor cannot be started.

9. Preparations before starting up

(1) First, turn the motor handwheel by hand to run the machine for 1 to 3 cycles, and check if there is any jamming.

(2) Check whether the vacuum meets the requirements. (Gauge pressure -0.06Mpa)

(3) When changing the mold, check carefully whether the metering plate, upper and lower modules, shift forks, guide grooves, etc. are worn out. If they are too worn, they should be updated.

(4) Check whether the capsules and materials meet the process requirements. If they are unqualified, they are not allowed to start production.