1. Preparation
Safety preparation:
Make sure the soft capsule machine has been shut down and the power supply is cut off to avoid accidental startup during operation, causing personal injury or equipment damage.
Prepare the necessary tools, such as wrenches, screwdrivers, pullers (if the shaft connection of the old blade needs to be removed), protective gloves and goggles, etc. to ensure safe operation.
2. Remove the old blades
Locate the fan position:
Find the fan position in the drying system, and determine the installation method of the fan and the connection method of the blade according to the structure and operation manual of the equipment.
Remove the protective cover and housing (if any):
Use a screwdriver or wrench to remove the protective cover and housing of the fan. These parts are usually fixed by screws or buckles. Place the removed parts properly to prevent loss or damage.
Remove the old blades:
Shaft connection method: If the blade is connected to the shaft by a key connection or a set screw, first use a wrench to loosen the set screw. For a key connection, you may need to use a puller to remove the blade from the shaft. When using a puller, clamp the puller's claws on the hub of the blade, then rotate the puller's screw to smoothly pull the blade off the shaft. Be careful not to damage the shaft during operation.
Bolted connection method: If the blade is fixed to the hub by bolts, use the corresponding wrench to unscrew the bolts and carefully remove the old blade. During the disassembly process, keep a record of the position and connection method of each component for subsequent installation.
3. Install new blades
Check new blades:
Before installing new blades, check whether the size, shape and quality of the new blades meet the requirements. Make sure that the new blades have no obvious deformation, cracks or other damage, and that their specifications are consistent with the original blades to ensure the performance of the fan.
Install the new blade on the shaft:
Shaft connection method: Put the hub of the new blade on the shaft. For key connection, ensure that the keyway is aligned and the key is correctly inserted into the keyway to form a tight connection between the blade and the shaft; for fixing by set screws, after installing the blade in the appropriate position, use a wrench to tighten the set screws to ensure that the blade is firmly fixed on the shaft, but do not over-tighten to avoid damaging the shaft or blade.
Bolt connection method: Align the new blade with the installation position of the hub, fix it with bolts and nuts, tighten the bolts according to the specified torque, and use a torque wrench to ensure that the tightening torque meets the requirements to avoid loosening or damage to the blade due to insufficient or excessive tightening torque.
IV. Reassembly and testing
Reinstall the protective cover and housing:
Reinstall the previously removed protective cover and housing according to the original position and connection method, and use a screwdriver or wrench to tighten the screws or buckles to ensure that the protective cover and housing are firmly installed to protect the fan and the operator.
Debugging and inspection:
Reconnect the power supply, start the drying system of the soft capsule machine, and observe the operation of the fan. Check whether the fan runs smoothly after the new blades are installed, and whether there is any abnormal vibration, noise or imbalance. Use an anemometer to measure the wind speed of the fan to ensure that the new blades can provide sufficient air volume to meet the needs of the drying system.
V. Record and subsequent maintenance
Record replacement information:
Record the time of fan blade replacement, the specifications of the new blades, the replacement personnel and other information in the equipment maintenance log for subsequent equipment maintenance and management.
During the subsequent use process, pay close attention to the operation of the fan, observe the performance of the new blades, and ensure its long-term stable operation.