Pre-Start Preparation
1. Environmental Check: Confirm that the temperature and humidity (typically 20-25℃, humidity <20%) and pressure differential in the drying room meet the requirements. Check that water, electricity, and gas are normal.
2. Equipment Check: Ensure the drum is clean and intact, the sensors on the cover correspond to the base switch, and the valve nuts are tightened.
3. Material Preparation: Pour wet material (such as soft capsules) into the drum, filling it no more than 3/4 full.
Start-up and Operation
1. Starting the Drum: Start the equipment according to the "Capsule Tumbler Dryer Operating Procedures" and set the speed (usually three levels: high, medium, and low, such as 48 rpm, 40 rpm, and 30 rpm).
2. Drying Process: The material is evenly lifted within the drum by the lifting plates, allowing for full contact with hot air for heat exchange. The drying time is typically 7-16 hours. 3. Discharge: After drying, adjust the rotation direction of the drum to the discharge direction (e.g., right turn), and the capsules will be automatically discharged.
Shutdown and Maintenance
1. Shutdown: After emptying the material, turn off all motor power and the main power supply.
2. Cleaning and Inspection: Clean any residual material from the drum, and check the lifting plates and transmission components for damage, preparing for the next use.
Precautions
1. Safety First: Never put your hands or hard objects into the drum while the equipment is running to prevent injury or damage to the mold.
2. Regular Maintenance: Check the lubrication of bearings, gears, and other transmission components, and promptly clean any adhering material from the lifting plates to keep the equipment clean.
3. Troubleshooting: If you encounter abnormal noise or vibration, stop the machine immediately for inspection. Refer to relevant guidelines for common faults.